Module 2 Challenge :Project Planning: Putting It All Together (Google Project Management Professional Certificate) Answers 2025
1. What is included in the project plan? (Select all)
✅ People
✅ Time
❌ Retrospectives
✅ Tasks
Explanation:
A project plan includes who (people), when (time), and what (tasks). Retrospectives happen after execution.
2. How can a PM account for potential vendor delays?
❌ Split the delivery task
❌ Limit number of books
✅ Add a project buffer
❌ Communicate daily
Explanation:
A buffer protects the schedule from external delays.
3. How much float do tasks on the critical path have?
❌ One day
✅ Zero days
❌ One month
❌ One week
Explanation:
Critical path tasks cannot be delayed at all without affecting the project end date.
4. PM listens, understands personal reasons, plans new options → Skill used?
❌ Using patience
❌ Negotiating effectively
❌ Asking the right questions
✅ Practicing empathy
Explanation:
The PM is understanding the teammate’s situation—this is empathy.
5. What document highlights tasks, assignments, and timeline?
✅ Project plan
❌ Risk assessment
❌ Team retrospective
❌ Project proposal
Explanation:
The project plan outlines the roadmap: tasks, owners, and schedule.
6. Speaking with SMEs to understand details illustrates which best practice?
❌ Recognize and plan for the inevitable
❌ Give yourself time to plan
✅ Understand deliverables, milestones, tasks
❌ Achieve team buy-in
Explanation:
Gathering detailed information defines what must be done.
7. Strategies to help a team meet a deadline (Select all)
❌ Rush planning
✅ Streamline tasks
✅ Increase team size
✅ Eliminate unnecessary tasks
Explanation:
Rushing planning causes errors; the others improve efficiency or capacity.
8. How to mitigate storm disruption?
❌ Remind team to work during storm
❌ Stay positive
✅ Add task buffers
❌ Assign more tasks
Explanation:
Weather is a known risk; buffers protect the schedule.
9. Strategy to estimate earliest & latest start dates?
✅ Use the forward pass or backward pass
❌ Develop a RACI chart
❌ Review goals
❌ List dependencies
Explanation:
Forward/backward pass is the CPM method for calculating start and finish times.
10. What information is on Kanban cards?
❌ Status only
✅ Information required to complete the task
❌ Retrospective notes
❌ Budget
Explanation:
Kanban cards contain key task details; the columns (not cards) show status.
🧾 Summary Table
| Q No. | Correct Answer(s) |
|---|---|
| 1 | People, Time, Tasks |
| 2 | Add a project buffer |
| 3 | Zero days |
| 4 | Practicing empathy |
| 5 | Project plan |
| 6 | Understand deliverables/milestones/tasks |
| 7 | Streamline tasks, increase team size, eliminate unnecessary tasks |
| 8 | Add task buffers |
| 9 | Forward/backward pass |
| 10 | Info required to complete task |