Module 1 Challenge :Project Planning: Putting It All Together (Google Project Management Professional Certificate) Answers 2025
1. First meeting among team, stakeholders, and sponsor
✅ A project kick-off meeting
❌ A stakeholder approval meeting
❌ A milestone planning meeting
❌ A team reflection meeting
Explanation:
The kick-off meeting formally starts the project with all major contributors.
2. Third major planning component after schedule + costs
❌ A feedback form
❌ A team performance chart
❌ A risk management plan
✅ A work breakdown structure
Explanation:
The three major components of planning are:
-
Schedule
-
Costs
-
Work Breakdown Structure (WBS)
3. Items stakeholders must approve before planning (Select all)
✅ Project scope
✅ Project goals
✅ Project deliverables
❌ Project name
Explanation:
Stakeholders approve core inputs—not the project name.
4. Team member unavailable → discussing adding resources updates:
❌ Budgeting
❌ Task management
❌ Forecasting
✅ Risk management
Explanation:
Team availability issues represent resource risk and must be updated in the risk management plan.
5. Discussing tools & communication methods in a kick-off meeting represents:
✅ Collaboration
❌ Roles
❌ Background
❌ Goals and scope
Explanation:
Collaboration section covers tools, meetings, and communication channels.
6. What PM should do after the kick-off?
❌ Ensure right people invited to next meeting
✅ Send a follow-up email summarizing key points and action items
❌ Schedule another meeting
❌ Immediately start the project
Explanation:
A follow-up email ensures clarity and alignment before work begins.
7. Tasks for opening a new café (Select all)
✅ Research equipment
❌ Create a new staff team (this is a deliverable, not a task)
✅ Research new locations
✅ Host a grand opening
✅ Create marketing content
Explanation:
Tasks are actionable steps; forming a full team is a larger deliverable.
8. Consequences of missing a milestone (Select all)
✅ Client could withhold payments
✅ Delay in schedule
❌ Team morale will increase
✅ Number of tasks may increase
✅ More resources may be needed
Explanation:
Missed milestones cause delays, added work, and resource strain—not improved morale.
9. After identifying milestones, next step is:
✅ Assign the deadlines
❌ Assign tasks to team members
❌ Execute the project
❌ Set a new budget
Explanation:
Milestones must be time-bound, so deadlines come next.
10. When assigning tasks, besides timeline, consider:
✅ Overall workload
❌ Task novelty
❌ Task interest
❌ Team member seniority
Explanation:
Balancing workload ensures fairness and efficiency.
🧾 Summary Table
| Q No. | Correct Answer(s) | Key Concept |
|---|---|---|
| 1 | Kick-off meeting | First planning-phase meeting |
| 2 | Work breakdown structure | Third major planning component |
| 3 | Scope, goals, deliverables | Stakeholder approval items |
| 4 | Risk management | Resource availability risk |
| 5 | Collaboration | Tools & communication |
| 6 | Follow-up email | Post kick-off action |
| 7 | Equipment, locations, grand opening, marketing | Café project tasks |
| 8 | Payment delays, schedule delays, more tasks, more resources | Milestone consequences |
| 9 | Assign deadlines | Milestone setup |
| 10 | Overall workload | Task assignment criteria |