Activity: Assign project roles and responsibilities in a RACI chart Answer 2025 (Project Initiation: Starting a Successful Project)
Activity-Template_-RACI-Chart—Phase-2 – Click here
Question 1
Did you complete this activity?
-
Yes
-
No
✅ Correct Answer: Yes
🔹 Explanation:
This is a completion check. You only need to confirm you’ve worked through the activity.
Question 2
In the RACI model, which role completes the work for a task or deliverable?
-
Responsible
-
Accountable
-
Consulted
-
Informed
✅ Correct Answer: Responsible
🔹 Explanation:
“Responsible” individuals do the work to complete the task or deliverable.
Question 3
What key questions should you consider when deciding who should be informed about a task? (Select all that apply.)
-
Who is affected by the outcome?
-
Who is invested in task completion, but not directly involved in the work?
-
Which department manages the work?
-
Who are the subject matter experts (SMEs) for the task?
✅ Correct Answer: Who is affected by the outcome; Who is invested in task completion, but not directly involved in the work
🔹 Explanation:
“Informed” are stakeholders who need updates because they are impacted or invested, but they don’t actively do the work.
Question 4
In your completed RACI chart, how many stakeholders are accountable for the “code the landing page” task?
-
0
-
1
-
2 or more
✅ Correct Answer: 1
🔹 Explanation:
By definition, only one stakeholder is accountable for each deliverable to avoid confusion. For coding, the Web Manager (final decisions) is Accountable, while the Web Developer is Responsible.
Question 5
In your completed RACI chart, who is responsible for creating the landing page mockup?
-
The Web Manager
-
The Graphic Designer
-
The Web Designer
-
The Web Developer
✅ Correct Answer: The Web Designer
🔹 Explanation:
The Web Designer creates the mockup (design + functionality). Graphic Designer and Content Writer provide input, but Responsible is the Web Designer.