Activity: Assign project roles and responsibilities in a RACI chart Answer 2025 (Project Initiation: Starting a Successful Project)

Activity-Template_-RACI-Chart—Phase-2 – Click here

Question 1

Did you complete this activity?

  • Yes

  • No

Correct Answer: Yes

🔹 Explanation:
This is a completion check. You only need to confirm you’ve worked through the activity.


Question 2

In the RACI model, which role completes the work for a task or deliverable?

  • Responsible

  • Accountable

  • Consulted

  • Informed

Correct Answer: Responsible

🔹 Explanation:
“Responsible” individuals do the work to complete the task or deliverable.


Question 3

What key questions should you consider when deciding who should be informed about a task? (Select all that apply.)

  • Who is affected by the outcome?

  • Who is invested in task completion, but not directly involved in the work?

  • Which department manages the work?

  • Who are the subject matter experts (SMEs) for the task?

Correct Answer: Who is affected by the outcome; Who is invested in task completion, but not directly involved in the work

🔹 Explanation:
“Informed” are stakeholders who need updates because they are impacted or invested, but they don’t actively do the work.


Question 4

In your completed RACI chart, how many stakeholders are accountable for the “code the landing page” task?

  • 0

  • 1

  • 2 or more

Correct Answer: 1

🔹 Explanation:
By definition, only one stakeholder is accountable for each deliverable to avoid confusion. For coding, the Web Manager (final decisions) is Accountable, while the Web Developer is Responsible.


Question 5

In your completed RACI chart, who is responsible for creating the landing page mockup?

  • The Web Manager

  • The Graphic Designer

  • The Web Designer

  • The Web Developer

Correct Answer: The Web Designer

🔹 Explanation:
The Web Designer creates the mockup (design + functionality). Graphic Designer and Content Writer provide input, but Responsible is the Web Designer.