Module 6 Challenge :Project Execution: Running the Project (Google Project Management Professional Certificate) Answers 2025
1. What type of project does this describe?
❌ A successful project
❌ A never-ending project
❌ A deadline project
✅ An abandoned project
Explanation:
If the team lacks required skills and cannot complete deliverables, the project becomes abandoned due to inability to progress.
2. After confirming all work is complete, what should the PM do next?
❌ Send a final email to stakeholders.
✅ Make sure all project management processes have been executed.
❌ Skip asking for sign-off.
❌ Adjust the deadline.
Explanation:
Before final closure, the PM must ensure all PM processes (sign-off, documentation, approvals) are fully completed.
3. When do milestones need a closing process?
❌ If the team thinks it wastes time
✅ If milestones won’t be re-addressed later
❌ If there are more milestones than tasks
❌ If a stakeholder requested it
Explanation:
A closing process is needed when a milestone won’t come up again, so the team fully evaluates and closes it.
4. What items can be included in a project closeout report? (Select all)
✅ Next steps and future considerations
❌ Confidential or proprietary information
❌ All future projects
✅ Project timelines
Explanation:
Closeout reports contain timelines, next steps, final insights, but not sensitive or unrelated future project details.
5. Purpose of the impact report
✅ Demonstrate how the project went and discuss the impact of its product/service
❌ Review the project with team members
❌ Protect scope
❌ Decide if milestones need closing
Explanation:
Impact reports highlight results, value, and impact of the completed project.
6. What item is missing from the closeout report?
❌ Next steps
❌ Open items
❌ Key accomplishments
✅ Lessons learned
Explanation:
The scenario covers accomplishments, open items, next steps, timeline, resources—but not lessons learned, which is required.
7. Fill in the blank
When closing a project, gather _____ from your team.
❌ opinions and biases
❌ rewards
✅ feedback
❌ compliments
Explanation:
Feedback helps improve processes and enhances future project management.
8. Final deliverable never reached customer due to poor handoff — project type?
❌ Unwritten
✅ Abandoned
❌ Unapproved
❌ Never-ending
Explanation:
A project that fails at handoff and never delivers is considered abandoned.
9. What document gives information on past similar projects?
✅ The project’s closeout report
❌ Stakeholder feedback survey
❌ Team performance review
❌ Statement of work
Explanation:
Closeout reports document what happened, lessons, timelines, results—useful for future reference.
10. A meeting to discuss successes, failures, and improvements is a _____.
✅ retrospective
❌ closeout
❌ status update
❌ stakeholder review
Explanation:
A retrospective specifically focuses on success, failure, and improvements.
🧾 Summary Table
| Q# | Correct Answer(s) | Key Concept |
|---|---|---|
| 1 | An abandoned project | Project failure types |
| 2 | Ensure all PM processes executed | Closure process |
| 3 | When milestones won’t be revisited | Milestone closure |
| 4 | Next steps, timelines | Closeout report content |
| 5 | Show project impact | Impact report |
| 6 | Lessons learned | Closeout components |
| 7 | Feedback | Continuous improvement |
| 8 | Abandoned | Failed handoff |
| 9 | Closeout report | Historical project reference |
| 10 | Retrospective | Reflection meeting |