Graded Quiz: Risk Assessment and Mitigation :Business Analysis: Project and Stakeholder Management (IBM Business Analyst Professional Certificate) Answers 2025
Question 1
What is the first step to take before addressing the team’s challenges?
❌ Create a risk mitigation strategy
✅ Prepare a clear and concise agenda for the conversation
❌ Develop a project management plan
❌ Reassess scope, goals, and timeline
Explanation:
Before any effective discussion, you should prepare an agenda to keep the conversation focused and productive.
Question 2
Which communication method best addresses stakeholder concerns in a mid-project review?
❌ Written communication
❌ Presentation
❌ Oral communication
✅ Interpersonal communication
Explanation:
Interpersonal communication allows two-way dialogue, addressing concerns, clarifying doubts, and aligning expectations.
Question 3
What does the “Coherent” aspect of the 5 Cs of communication mean?
❌ Ensure flow of words using graphics
✅ Ensure the flow of ideas is logical with introductions and summaries
❌ Ensure stakeholder needs are factored
❌ Ensure grammar and spelling are accurate
Explanation:
Coherent communication means ideas are logically structured and easy to follow.
Question 4
Primary advantage of in-person communication?
❌ Facilitate regular updates
✅ Allow team members to work together synchronously and collaborate effectively
❌ Prevent risks
❌ Reduce follow-up meetings
Explanation:
In-person communication supports real-time collaboration and immediate feedback.
Question 5
Which component identifies who is responsible for communication items?
✅ Owner
❌ Timing
❌ Medium
❌ Purpose
Explanation:
The Owner specifies the individual accountable for managing communication.
Question 6
Where is the definition and frequency of status reporting documented?
❌ Risk assessment plan
✅ Communications management plan
❌ Work breakdown structure
❌ Stakeholder register
Explanation:
The communications management plan defines what is communicated, how often, and to whom.
Question 7
What is included in periodic work performance reports?
❌ Project plan
❌ Resource allocation sheet
✅ Dashboards
❌ Budget variances
Explanation:
Dashboards summarize performance information for stakeholders.
Question 8
Final step in planning conversations with stakeholders and the team?
❌ Choose the correct mode
✅ Follow up
❌ Define your goals
❌ Prepare an agenda
Explanation:
After the conversation, follow-up ensures actions and decisions are implemented.
Question 9
What is defined as “raw” data by PMI?
❌ Work Performance Reports (WPR)
❌ Project Status Report
❌ Performance Metrics
✅ Work Performance Data (WPD)
Explanation:
Work Performance Data is raw, unprocessed information collected during project execution.
Question 10
Which plan component determines how communication is conducted?
❌ Purpose
✅ Format or Medium
❌ Audience
❌ Timing
Explanation:
The format/medium defines whether communication is via email, meeting, report, dashboard, etc.
🧾 Summary Table
| Question | Correct Answer | Key Concept |
|---|---|---|
| Q1 | Prepare agenda | Conversation planning |
| Q2 | Interpersonal communication | Stakeholder alignment |
| Q3 | Logical flow of ideas | 5 Cs – Coherent |
| Q4 | Real-time collaboration | In-person communication |
| Q5 | Owner | Communication responsibility |
| Q6 | Communications plan | Status reporting |
| Q7 | Dashboards | Performance reporting |
| Q8 | Follow up | Effective communication |
| Q9 | Work Performance Data | PMI terminology |
| Q10 | Format / Medium | Communication method |