Module 3 Challenge :Agile Project Management (Google Project Management Professional Certificate) Answers 2025
1. Why is the Product Backlog a “living artifact”?
✅ The Product Owner can add items at any time.
❌ Team members only add at the end of a Sprint
❌ Product Owner only adds at the end of a Sprint
❌ Stakeholders can add items at any time
Explanation:
The Product Backlog is constantly evolving because the Product Owner can update it anytime.
2. Including a clear Definition of Done makes a user story _____.
❌ independent
❌ negotiable
❌ valuable
✅ estimatable
Explanation:
Clear DoD helps the team understand effort → makes the story estimatable (I.N.V.E.S.T.).
3. Private estimates prevent influencing others. This avoids what?
❌ Build team trust
✅ Avoid anchoring bias
❌ Lead to effort discovery
❌ Promote inclusivity
Explanation:
Anchoring bias = when the first estimate influences others. Private estimates avoid this.
4. Setting the initial Sprint duration refers to what Scrum concept?
❌ Time frame
❌ Schedule
❌ Interval
✅ Timebox
Explanation:
Scrum uses timeboxes to define fixed lengths for Sprints and events.
5. Which event includes velocity, availability, task planning?
❌ Sprint Review
❌ Sprint Retrospective
✅ Sprint Planning
❌ Daily Scrum
Explanation:
Sprint Planning determines capacity, velocity, availability, and task ownership.
6. What typically occurs during the Sprint Review? (Select all)
❌ Synchronize & prioritize team activities
❌ Discuss how to work better as a team
✅ Explore which items should be considered done in the Backlog
✅ Demonstrate and inspect the product
Explanation:
Sprint Review focuses on inspecting the increment and adjusting the product backlog.
7. How can the Scrum Master help a quiet team member participate? (Select all)
✅ Quiet journaling for first 10 minutes
❌ Ask them to speak first
❌ Make no changes
✅ Pair team members for discussion
Explanation:
Creating psychological safety requires gentle methods—not forcing someone to speak.
8. Overall goal of a burndown chart?
✅ Keep the team aware of how they’re doing against their goals
❌ Quantify individual performance
❌ Compare productivity among teams
❌ Communicate with outside stakeholders
Explanation:
Burndown shows team progress vs. remaining work.
9. Compare Kanban board vs. Scrum board
❌ Scrum board is more visual
❌ Kanban is better for tracking Sprint tasks
✅ They’re essentially the same tool with minor differences
❌ Teams have little use for Kanban
Explanation:
Both visualize work; main differences = workflow vs. sprint focus.
10. Tools that make progress visible embody which Scrum pillar?
❌ Inspection
✅ Transparency
❌ Adaptation
❌ Commitment
Explanation:
Transparency = making work visible, clear, and accessible to all team members.
🧾 Summary Table
| Q# | Correct Answer(s) | Key Concept |
|---|---|---|
| 1 | PO can add anytime | Backlog evolution |
| 2 | Estimatable | I.N.V.E.S.T. |
| 3 | Avoid anchoring bias | Estimation behavior |
| 4 | Timebox | Scrum time limits |
| 5 | Sprint Planning | Capacity & planning |
| 6 | Done items, demo product | Sprint Review |
| 7 | Quiet journaling, pairing | Inclusivity |
| 8 | Track progress vs goals | Burndown chart |
| 9 | Same tool, minor differences | Kanban vs Scrum |
| 10 | Transparency | Scrum pillars |