Final Exam: Business Analysis: Project and Stakeholder Management :Business Analysis: Project and Stakeholder Management (IBM Business Analyst Professional Certificate) Answers 2025
Question 1
Which project management approach fits frequent changes, feedback, and testing?
❌ Predictive
❌ Iterative
❌ Incremental
✅ Agile
Explanation:
Agile supports frequent feedback, changing scope, continuous updates, and usability testing.
Question 2
After defining the problem and objectives, what is the next BA step?
❌ Needs assessment
✅ Stakeholder engagement
❌ Elicitation
❌ Requirements tracking
Explanation:
Once objectives are clear, the next step is to identify and engage stakeholders.
Question 3
Which model includes one-time planning followed by repeated design–code–test cycles?
❌ Six Sigma
✅ Extreme Programming software development process
❌ Lean model
❌ Waterfall model
Explanation:
Extreme Programming (XP) uses short, repeated iterations after initial planning.
Question 4
Best certification for an Associate Business Analyst?
❌ PMI-ACP
❌ CBAP
✅ CCBA
❌ ECBA
Explanation:
CCBA is designed for professionals with some experience handling medium-sized projects.
Question 5
What does ‘R’ in RACI stand for?
❌ Reporting
❌ Reaction
❌ Reinforcement
✅ Responsible
Explanation:
Responsible refers to the person who performs the task.
Question 6
Which document defines stakeholder engagement levels and strategies?
❌ Project Charter
❌ Stakeholder Register
✅ Stakeholder Engagement Plan
❌ Project Management Plan
Explanation:
The Stakeholder Engagement Plan documents current vs desired engagement and actions.
Question 7
What does the “Tell” strategy refer to?
❌ Eliciting opinions
✅ Explain the project, its importance, and roles
❌ Provide post-project feedback
❌ Delegate responsibilities
Explanation:
The Tell (Directing) style focuses on clear instructions and guidance.
Question 8
What comes after initiation in PMBOK6?
❌ Monitoring
❌ Controlling
✅ Planning
❌ Execution
Explanation:
PMBOK sequence: Initiation → Planning → Execution → Monitoring & Controlling → Closing.
Question 9
Which is a collaboration tool?
❌ Adobe Photoshop
❌ Microsoft Excel
❌ Microsoft Word
✅ Slack
Explanation:
Slack enables real-time collaboration and communication.
Question 10
What does a unanimous decision mean?
❌ More than 50% support
✅ 100% support from voting members
❌ Largest group decides
❌ Simple majority needed
Explanation:
Unanimous means everyone agrees.
Question 11
Which approach fits high technological complexity?
❌ Adaptive lifecycles
✅ Agile lifecycles
❌ Predictive lifecycles
❌ Iterative lifecycles
Explanation:
Agile handles complex, uncertain, technology-driven environments well.
Question 12
What does ‘P’ in the DEEP backlog model stand for?
❌ Precision
❌ Precaution
✅ Prioritize
❌ Popularity
Explanation:
DEEP = Detailed appropriately, Estimated, Emergent, Prioritized.
Question 13
Key benefit of the project initiation phase?
❌ Define timeline and budget
❌ Post-project evaluation
❌ Assign roles
✅ Ensuring the project meets organizational needs
Explanation:
Initiation ensures strategic alignment and business value.
Question 14
Primary responsibility during planning phase?
❌ Defining scope
❌ Creating timeline
❌ Documenting personal needs
✅ Developing a risk management plan
Explanation:
Planning focuses on risk identification, analysis, and mitigation planning.
Question 15
A newly emerged, unanticipated requirement represents what type of risk?
❌ Controlled risk
❌ Managed risk
❌ Known risk
✅ Unknown risk
Explanation:
Unanticipated challenges are unknown risks.
Question 16
In risk metalanguage, what does “bad weather” represent?
✅ Risk cause
❌ Risk event
❌ Risk response
❌ Risk impact
Explanation:
A cause is the source that triggers the risk.
Question 17
Which strategy requires high-level approval (e.g., sponsor)?
❌ Exploitation
❌ Mitigation
❌ Acceptance
✅ Escalation strategy
Explanation:
Escalation is used when authority exceeds the PM’s control.
Question 18
BABOK guideline for effective communication?
❌ Limit feedback
❌ Minimize stakeholder involvement
✅ Facilitate effective meetings
❌ Avoid documentation
Explanation:
BABOK emphasizes structured, effective communication and meetings.
Question 19
Which feature describes active listening?
❌ Responding only
❌ Avoiding eye contact
❌ Focusing on response
✅ Use of verbal and nonverbal cues
Explanation:
Active listening includes eye contact, nodding, paraphrasing, and feedback.
Question 20
Essential component of a status report?
❌ Appraisal requests
✅ Risk assessment
❌ Personal notes
❌ Glossary
Explanation:
Status reports include risks, issues, progress, and variances.
🧾 Summary Table
| Q# | Correct Answer | Key Concept |
|---|---|---|
| 1 | Agile | Adaptive projects |
| 2 | Stakeholder engagement | BA flow |
| 3 | Extreme Programming | Iterative cycles |
| 4 | CCBA | Associate BA |
| 5 | Responsible | RACI |
| 6 | Stakeholder Engagement Plan | Stakeholder mgmt |
| 7 | Explain roles | Tell strategy |
| 8 | Planning | PMBOK |
| 9 | Slack | Collaboration |
| 10 | 100% agreement | Voting |
| 11 | Agile lifecycles | Tech complexity |
| 12 | Prioritize | DEEP backlog |
| 13 | Strategic alignment | Initiation |
| 14 | Risk plan | Planning |
| 15 | Unknown risk | Risk type |
| 16 | Risk cause | Metalanguage |
| 17 | Escalation | Authority |
| 18 | Effective meetings | BABOK |
| 19 | Verbal & nonverbal cues | Active listening |
| 20 | Risk assessment | Status report |