Graded Quiz: Project Planning and Execution for Business Analysts :Business Analysis: Project and Stakeholder Management (IBM Business Analyst Professional Certificate) Answers 2025

Question 1

Which statement correctly describes an advantage of using project lifecycles?

Provides a structure for project delivery
❌ Provides more flexibility for the project
❌ Ensures assured project success
❌ Eliminates the need for project planning

Explanation:
Project lifecycles provide a structured framework that guides activities from initiation to closure.


Question 2

Which backlog is used to organize specific tasks supporting user stories in an adaptive project?

❌ Product backlog
❌ Product increment backlog
Sprint backlog
❌ Work breakdown structure

Explanation:
The Sprint Backlog contains tasks selected to implement user stories during a sprint.


Question 3

Crucial responsibility of the project manager during initiation?

❌ Developing a communication plan
❌ Monitoring project progress
Developing key documents for approval (business case, charter, stakeholder register)
❌ Managing risks and mitigation

Explanation:
During initiation, the PM focuses on authorizing documents to formally start the project.


Question 4

After developing scope, budget, and schedule—what’s next?

Establish the scope, schedule, and cost baselines
❌ Define project scope and objectives
❌ Outline team roles and responsibilities
❌ Approve documents for record-keeping

Explanation:
Baselines are set to measure performance and control changes.


Question 5

Assembling hardware before software refers to which dependency?

❌ Internal dependencies
❌ Discretionary dependencies
Mandatory dependencies
❌ External dependencies

Explanation:
Mandatory dependencies are inherent to the work (physical or logical necessity).


Question 6

Final step in developing a business case?

❌ Create the business strategy
❌ Establish communication strategy
❌ Define the project
Justify the project

Explanation:
The business case concludes by justifying value, benefits, and feasibility.


Question 7

Tool to break down scope into manageable activities?

❌ Stakeholder register
❌ Stakeholder engagement plan
❌ Traceability matrix
Work breakdown structure

Explanation:
A WBS decomposes scope into work packages and activities.


Question 8

Which artifact includes specific tasks derived from a user story?

❌ Product backlog
❌ User story
❌ Product increment
Sprint backlog

Explanation:
The Sprint Backlog contains tasks needed to complete selected user stories.


Question 9

Best description of the benefit of the initiation phase?

❌ Ensures alignment with project objectives
❌ Determines effectiveness of risk management
Provides overall view of the project
❌ Facilitates task completion

Explanation:
Initiation establishes high-level vision, scope, and feasibility.


Question 10

Component of an integrated change control program?

Change log
❌ Stakeholder engagement plan
❌ Stakeholder register
❌ Project charter

Explanation:
A Change Log tracks requested, approved, and rejected changes.


🧾 Summary Table

Question Correct Answer Key Concept
Q1 Provides structure Project lifecycle
Q2 Sprint backlog Agile delivery
Q3 Key approval documents Initiation
Q4 Establish baselines Planning control
Q5 Mandatory dependency Scheduling
Q6 Justify the project Business case
Q7 WBS Scope management
Q8 Sprint backlog Agile artifacts
Q9 Overall project view Initiation
Q10 Change log Change control