Module 1 Challenge :Project Execution: Running the Project (Google Project Management Professional Certificate) Answers 2025
1. A major disaster shutting down the facility is called:
❌ A start
❌ A changelog
❌ A deviation
✅ A risk
Explanation:
Unexpected events that can impact a project are classified as risks.
2. What should PMs track to ensure deadlines are met?
❌ Track costs
❌ Track successes
✅ Track tasks as they progress and as milestones approach
❌ Track stakeholder engagement
Explanation:
Monitoring task progress ensures the project stays on schedule.
3. Stakeholder wants a granular breakdown of tasks + time remaining → chart?
❌ Gantt chart
❌ Project status report
❌ Roadmap
✅ Burndown chart
Explanation:
Burndown charts show work remaining over time with granular detail.
4. How does a roadmap differ from a Gantt chart?
✅ A roadmap tracks big milestones & high-level overview; a Gantt is useful for large projects with many dependencies.
❌ Roadmap for dependencies / Gantt high level
❌ Roadmap measures time vs work left
❌ Roadmap dependency tool / Gantt burndown style
Explanation:
Roadmap = high-level milestone view
Gantt = detailed task sequencing & dependencies
5. Contractor delays a key task → which triple constraint is impacted most?
❌ Budget
❌ Scope
✅ Timeline
Explanation:
Delays directly affect the schedule.
6. Scope creep during execution signifies a:
❌ Milestone
❌ Task
❌ Concern
✅ Risk
Explanation:
Scope changes add risk to cost, time, and deliverables.
7. Steps in dependency management (Select all)
✅ Efficient communication
❌ Eliminating dependencies
✅ Recording dependencies
✅ Continuous monitoring and control
Explanation:
Dependencies cannot always be removed but must be tracked and monitored.
8. Matrix of impact × probability → PM is determining:
❌ Risk appetite
✅ Risk exposure
❌ Risk dependencies
❌ Risk management
Explanation:
Exposure = likelihood × impact.
9. In escalation email, describing how obstacle delays next phase represents:
✅ Explain the consequences
❌ Make a request
❌ Maintain a friendly tone
❌ Explain the issue
Explanation:
Consequences describe future impact of the issue.
10. Problems avoided by escalating issues (Select all)
✅ Bad compromises
❌ Risk appetite
✅ Trench wars
❌ Force majeure
Explanation:
Escalation prevents forced bad trade-offs and team conflict (“trench wars”).
11. ROAM technique → you find a workaround so risk is no longer a problem
❌ Resolved
❌ Owned
❌ Accepted
✅ Mitigated
Explanation:
Mitigation reduces or avoids the impact of the risk, often via workaround.
🧾 Summary Table
| Q No. | Correct Answer(s) |
|---|---|
| 1 | Risk |
| 2 | Track task progress & milestones |
| 3 | Burndown chart |
| 4 | Roadmap high-level; Gantt detailed dependencies |
| 5 | Timeline |
| 6 | Risk |
| 7 | Communication, recording, monitoring |
| 8 | Risk exposure |
| 9 | Explain the consequences |
| 10 | Bad compromises, trench wars |
| 11 | Mitigated |