Module 2 Challenge :Project Planning: Putting It All Together (Google Project Management Professional Certificate) Answers 2025

1. What is included in the project plan? (Select all)

✅ People
✅ Time
❌ Retrospectives
✅ Tasks

Explanation:
A project plan includes who (people), when (time), and what (tasks). Retrospectives happen after execution.


2. How can a PM account for potential vendor delays?

❌ Split the delivery task
❌ Limit number of books
✅ Add a project buffer
❌ Communicate daily

Explanation:
A buffer protects the schedule from external delays.


3. How much float do tasks on the critical path have?

❌ One day
✅ Zero days
❌ One month
❌ One week

Explanation:
Critical path tasks cannot be delayed at all without affecting the project end date.


4. PM listens, understands personal reasons, plans new options → Skill used?

❌ Using patience
❌ Negotiating effectively
❌ Asking the right questions
✅ Practicing empathy

Explanation:
The PM is understanding the teammate’s situation—this is empathy.


5. What document highlights tasks, assignments, and timeline?

✅ Project plan
❌ Risk assessment
❌ Team retrospective
❌ Project proposal

Explanation:
The project plan outlines the roadmap: tasks, owners, and schedule.


6. Speaking with SMEs to understand details illustrates which best practice?

❌ Recognize and plan for the inevitable
❌ Give yourself time to plan
✅ Understand deliverables, milestones, tasks
❌ Achieve team buy-in

Explanation:
Gathering detailed information defines what must be done.


7. Strategies to help a team meet a deadline (Select all)

❌ Rush planning
✅ Streamline tasks
✅ Increase team size
✅ Eliminate unnecessary tasks

Explanation:
Rushing planning causes errors; the others improve efficiency or capacity.


8. How to mitigate storm disruption?

❌ Remind team to work during storm
❌ Stay positive
✅ Add task buffers
❌ Assign more tasks

Explanation:
Weather is a known risk; buffers protect the schedule.


9. Strategy to estimate earliest & latest start dates?

✅ Use the forward pass or backward pass
❌ Develop a RACI chart
❌ Review goals
❌ List dependencies

Explanation:
Forward/backward pass is the CPM method for calculating start and finish times.


10. What information is on Kanban cards?

❌ Status only
✅ Information required to complete the task
❌ Retrospective notes
❌ Budget

Explanation:
Kanban cards contain key task details; the columns (not cards) show status.


🧾 Summary Table

Q No. Correct Answer(s)
1 People, Time, Tasks
2 Add a project buffer
3 Zero days
4 Practicing empathy
5 Project plan
6 Understand deliverables/milestones/tasks
7 Streamline tasks, increase team size, eliminate unnecessary tasks
8 Add task buffers
9 Forward/backward pass
10 Info required to complete task